Fishers of Men Participates in Another project in Richmond Starting September 12th 2009.
The home we are working on is in Richmond, TX at the corner of 10th and Preston. The new homeowners, Heather & "Pink" Turner, will be working along side of us. The Turners have 2 young children and live in a one bedroom home with no central heat and only one window AC unit. They have sewage that backs up into their yard, and they need your help! "Pink" is on disability and is an active volunteer at Fort Bend's Habitat Resale Center in Stafford. Heather is employed by Texana.
The build begins on September 12, 2009 and continue through the following
8-10 Saturdays. Please see the schedule below for more details.
Thank You for Your Help with the 2008 Rosenburg Build!
-from the Habitat Chapter Specialist to all volunteers (not just Fishers)
"I want to thank you for your support of the 2008 build in Rosenburg. Over the duration of the build, you provided help and encouragement including 253 person days of labor. I was awed at the faithfulness of those who showed up on very hot days to work so hard."
Fishers of men provided approximately 30% of the labor. God is so good! Let's do it again!!
Schedule
Details about the project for each Saturday of work are listed with the event. The schedule of activity is also a helpful guide for individuals to work especially when they may have a unique skill appropriate for the day. But remember, there's no experience necessary! Come as you are and help where you can.
- Prior to construction: all permits pulled, temporary electric pole activated, and slab poured. Sole & top plates to be laid out & marked prior to the 1st Saturday
(5 people - 4 hours) - September 12: Canceled due to rain - slab not poured yet!
Frame exterior and interior wall sections. Double top plate installed. Apply OSB sheathing around exterior of the house
(40-60 people) - September 19: Install roof trusses, sub-facia and facia. Install gable soffits, roof decking, hurricane straps, Tyvek, windows, and exterior doors
(40-60 people) - September 26: Install roofing felt, shingles, soffits, and attic stairs. Begin siding
(40-60 people) - ** September 28 - October 2: Call for rough plumbing, rough electrical, rough HVAC and get inspections
- October 3: Finish work from past three weeks. Use as a catch up week.
- October 10: Complete siding, soffits, exterior trim, insulate house (if framing inspection complete), paint with exterior primer and add sheetrock nailers
(30 people) - ** October 12 - October 16: Call for drywall if inspections complete. Typically the drywall is not complete by the next Saturday.
- October 17: Paint exterior, level site, sweep interior and remove trash. Paint baseboards and casing with primer. Go home early!
(25 people) - ** October 19 - October 23: We will typically blow texture during the week
(3 people - 3 hours) - October 24: Install interior doors & casing, bathroom vanity, baseboards, closet shelving, window stools, closet doors, etc. Assemble and install kitchen cabinets. Paint with interior primer
(25 people) - October 31: Finish work not completed. Use as catch up week.
- November 7: Finish remaining trim, install flooring, counter tops, and electrical fixtures (fans, lights, etc.). Paint interior walls and trim
(25 people). - ** November 9 - November 13: Call for final electrical, plumbing and HVAC installation. Carpet installed during the week.
- November 14: Install mini-blinds and landscape (grass & plants). Clean-up, touch-up.


